Nearly 30% of registered projects remain incomplete beyond their approved completion dates, raising concerns over regulatory enforcement and homebuyer protection.
By The Realty Times | Real Estate News Services
BENGALURU: Thousands of homebuyers in Karnataka
continue to face uncertainty as developers have failed to complete 3,145
housing projects within their approved deadlines, according to data from the
Karnataka Real Estate Regulatory Authority (K-RERA). The growing number of
delayed projects has raised serious concerns about construction delays,
financial losses and the effectiveness of regulatory mechanisms designed to
protect property buyers.
The issue affects homebuyers across the state, particularly
those who have invested their lifetime savings in residential properties and
are still waiting for possession despite making substantial payments to
developers.
Since its establishment in 2017, K-RERA has registered
10,621 real estate projects. Nearly 30% of these projects remain incomplete
even after their scheduled completion dates, highlighting the scale of the
problem in Karnataka's residential property market.
Government and Private Projects Also Affected
The list of projects that have missed their completion
deadlines includes developments undertaken by private real estate developers as
well as public-sector agencies.
These include projects associated with the Karnataka Slum
Development Board, Bangalore Development Authority (BDA), and various town and
city municipal corporations.
The presence of government-backed developments on the list
indicates that project delays are not limited to private builders but extend
across different segments of the state's housing sector.
Only 10% of Compensation Recovered
One of the major concerns highlighted by homebuyer
organisations is the difficulty in recovering compensation even after obtaining
favourable orders from the regulatory authority.
According to data compiled by the Forum for People's
Collective Efforts (FPCE), K-RERA has issued recovery certificates worth
approximately ₹1,253 crore in favour of homebuyers. However, only ₹129.03 crore
has reportedly been recovered so far.
This represents just around 10.3% of the total amount
covered by recovery certificates.
The substantial gap between compensation awarded and actual
recovery has added to the financial difficulties of affected homebuyers. Many
continue to pay home loan instalments and rental expenses simultaneously while
waiting for possession or refunds.
Homebuyers' Body Calls for Stronger Enforcement
The Forum for People's Collective Efforts (FPCE), an
organisation representing homebuyers, has raised concerns over the monitoring
and enforcement mechanisms of K-RERA.
The organisation has pointed out that inadequate scrutiny of
developers' quarterly progress reports and insufficient physical inspections of
construction sites may have contributed to the growing number of delayed
projects.
FPCE has also called for stronger coordination between
government departments and regulatory authorities to ensure that developers
fulfil their commitments.
Among its key recommendations is the formation of a
high-level coordination committee under the chairmanship of Karnataka's Chief
Secretary. The proposed committee would include senior officials from housing,
revenue and urban development departments, along with representatives of
K-RERA, BDA and homebuyer organisations.
RERA's Role in Protecting Homebuyers
The Real Estate (Regulation and Development) Act, 2016, was
introduced to improve transparency, accountability and discipline in India's
property sector.
Under the Act, developers are required to register eligible
projects, disclose approved completion timelines, provide regular construction
updates and comply with their commitments to buyers.
Homebuyers also have the right to seek relief through the
regulatory authority in cases involving delayed possession, non-compliance or
other violations of the Act.
However, the Karnataka situation highlights the challenges
involved in translating regulatory orders into actual relief for affected
buyers. Stronger monitoring, timely inspections and effective recovery of
compensation are increasingly being viewed as essential to restoring confidence
in the housing market.
A Wake-Up Call for India's Real Estate Industry
The growing number of delayed housing projects in Karnataka
serves as a reminder of the importance of responsible project development and
effective regulatory supervision.
For homebuyers, timely possession is not merely a
contractual commitment but a crucial financial and personal milestone.
Prolonged construction delays can affect family plans, increase financial
liabilities and undermine confidence in property investments.
The Karnataka developments also highlight the need for
prospective buyers to verify project registration, approved completion dates,
construction progress and the developer's track record before investing.