IBBI Overhauls Real Estate Insolvency Rules

New Framework to Protect Homebuyers and Speed Up Project Completion

By The Realty Times | Real Estate News Services

New Delhi: The Insolvency and Bankruptcy Board of India (IBBI) has introduced significant changes to the insolvency resolution framework for real estate companies, aiming to protect homebuyers, accelerate stalled housing projects and bring greater transparency to the resolution of financially distressed developers.

The regulator notified the Insolvency and Bankruptcy Board of India (Insolvency Resolution Process for Corporate Persons) (Fifth Amendment) Regulations, 2026, on October 30, 2026. The revised regulations introduce several measures to address long-standing challenges in resolving stressed real estate projects, particularly those involving developers with multiple residential and commercial developments.

The amendments are expected to make the insolvency process more project-oriented rather than treating all projects of a financially distressed developer as a single unit. This could help protect completed projects from unnecessary disruption while allowing greater attention to be given to unfinished developments.

According to IBBI, the changes are designed to facilitate viable project resolution, strengthen accountability and improve the participation of homebuyers and other stakeholders in the Corporate Insolvency Resolution Process (CIRP).

Project-Wise Resolution to Protect Completed Developments

One of the most important changes is the introduction of a mechanism to identify and potentially exclude individual real estate projects from the insolvency resolution process.

Under the revised regulations, when a developer has multiple projects, the Resolution Professional (RP) must present project-wise information before the Committee of Creditors (CoC) at its first meeting.

The information must include:

  • RERA registration details of each project.
  • Construction and completion status.
  • Possession and occupancy status.
  • Details of completed and incomplete units.
  • Other relevant information required to assess individual projects.

After examining these details, the Committee of Creditors can recommend excluding a particular project from the insolvency proceedings, provided the recommendation receives at least 66% of the voting share. The proposal, along with recorded reasons, must then be submitted to the Adjudicating Authority, which will consider the request.

This provision could be particularly beneficial for developers operating several projects, where financial difficulties in one development have affected completed or nearly completed properties in other locations.

Mandatory Technical and Cost-to-Complete Assessment

Another major reform is the introduction of a mandatory technical and cost-to-complete assessment for real estate projects undergoing insolvency proceedings.

Before inviting expressions of interest from prospective resolution applicants, the Resolution Professional must appoint suitably qualified and independent professionals, with prior approval from the Committee of Creditors, to evaluate each project.

The assessment will cover:

  • Actual construction progress and percentage of completion.
  • Regulatory approvals, permissions and RERA compliance.
  • Details of sold and unsold inventory.
  • Estimated expenditure required to complete the project.
  • Phase-wise funding requirements.
  • Realistic construction and possession timelines.
  • Potential risks and challenges affecting project completion.

The assessment will become part of the Information Memorandum and will be made available to prospective resolution applicants. This is expected to help investors and developers evaluate the financial viability of distressed projects and submit more realistic resolution proposals.

Separate Bank Accounts for Individual Projects

The amended regulations also strengthen financial discipline by requiring a separate bank account for every real estate project of a corporate debtor undergoing insolvency proceedings.

The Resolution Professional must periodically submit project-wise statements of receipts and payments, along with other financial information, to the Committee of Creditors.

The professional must also ensure compliance with fund-utilisation requirements under the Real Estate (Regulation and Development) Act, 2016 (RERA).

This measure is intended to improve financial transparency and prevent funds associated with one project from being improperly diverted to another development.

Faster Possession and Registration for Homebuyers

The revised regulations introduce greater flexibility in facilitating the handover of completed apartments, plots and buildings to eligible homebuyers.

Previously, individual requests for possession and registration could require separate consideration and approval by the Committee of Creditors.

Under the new framework, the CoC can either approve individual requests or provide an in-principle approval authorising the Resolution Professional to process such requests as and when they are received during the insolvency proceedings.

This provision could reduce procedural delays and help eligible homebuyers take possession of completed properties without repeatedly waiting for individual approvals.

Stronger Representation for Homebuyers

The amendments also seek to strengthen the role of homebuyers in the insolvency resolution process.

Homebuyers are recognised as financial creditors under the Insolvency and Bankruptcy Code (IBC) and participate in the Committee of Creditors as a class through an authorised representative (AR).

Under the revised provisions, the public announcement inviting claims must provide creditors in a class with a choice of three insolvency professionals to act as their authorised representatives. Brief professional profiles and information about their responsibilities must also be provided.

Furthermore, authorised representatives must submit minutes of their meetings with homebuyers to the Resolution Professional. The minutes of Committee of Creditors meetings must also record the views, concerns and opinions expressed by these representatives.

This is expected to improve communication between homebuyers and the decision-making authorities during insolvency proceedings.

Homebuyers and Regulatory Authorities in Monitoring Committees

The revised regulations also introduce changes to the composition of monitoring committees responsible for overseeing the implementation of approved resolution plans.

The monitoring committee must include an authorised representative of homebuyers or another allottee representative selected through a majority vote.

A representative of the concerned Real Estate Regulatory Authority (RERA) and, wherever applicable, a representative of the competent authority must also be included, subject to their agreement to participate.

The involvement of homebuyers and regulatory authorities is expected to improve monitoring of construction progress, regulatory approvals, statutory compliance and possession commitments.

Greater Transparency in Project Information

The amendments also strengthen disclosure requirements to ensure that prospective investors and resolution applicants have access to comprehensive information about distressed real estate projects.

The Information Memorandum must provide detailed project-wise information, including construction progress, available inventory, common areas and amenities, development potential, regulatory approvals, outstanding liabilities, litigation, statutory dues, regulatory proceedings and RERA bank account balances.

It must also identify homebuyers whose names appear in the developer's records or RERA records but who have not submitted claims during the insolvency process.

Details of their outstanding amounts and allotted units must be disclosed.

Importantly, the information must also reflect homebuyers' preferences regarding possession, conveyance, registration or transfer of title, refunds and other possible forms of settlement.

Resolution Plans Must Specify Possession Timelines

The amended regulations introduce specific requirements for resolution plans involving real estate companies.

Every resolution plan must provide project-wise details of sanctioned, constructed and under-construction units, with sold and unsold inventory clearly segregated.

It must also explain how the claims of homebuyers will be addressed, including through:

  • Handover of possession.
  • Execution of conveyance deeds.
  • Registration or transfer of property titles.
  • Refund of amounts paid.
  • Other forms of settlement.

Resolution plans must also specify project-wise, phase-wise or tower-wise construction completion and possession timelines, wherever applicable.

Additionally, periodic progress reports must be submitted to the monitoring committee to track implementation.

A Significant Development for India's Real Estate Sector

The latest IBBI reforms come against the backdrop of persistent delays in resolving financially distressed real estate companies, leaving thousands of homebuyers waiting for possession of their properties.

According to figures cited in reports on the regulatory changes, 221 out of 553 real estate insolvency cases admitted under the IBC were still ongoing as of September 30, 2025. These cases involved approximately 1.09 lakh homebuyers.

The prolonged resolution of stalled projects has remained a major concern for homebuyers, particularly when financially troubled developers operate multiple projects and insolvency proceedings affect developments that are otherwise completed or nearing completion.

The new framework attempts to address these challenges through project-wise financial management, independent technical assessments, improved stakeholder participation and clearly defined delivery commitments.

For the real estate industry, the amendments could also improve the attractiveness of stressed projects to potential investors and developers by providing better financial information and a clearer understanding of completion costs and regulatory obligations.

However, the actual impact will depend on how efficiently Resolution Professionals, Committees of Creditors, the National Company Law Tribunal (NCLT) and regulatory authorities implement the revised provisions.

The IBBI's latest amendments represent an important shift towards a more homebuyer-focused and project-specific approach to real estate insolvency in India. By prioritising project completion, transparency, accountability and stakeholder participation, the new framework seeks to address one of the biggest concerns in the housing sector: the prolonged uncertainty faced by buyers of stalled residential projects.

If effectively implemented, these changes could help revive financially distressed developments, facilitate faster possession and restore confidence among homebuyers and investors in India's real estate market.